Completed
Urban Road
Works
Upgrading Of Arizona Road (269M), Abed Roundabout Road (114M) And Richard Appiah Road (446M) - At Old Tafo
Old Tafo Municipal Assembly
Physical Completion
100%Map Location
Other Sub-Projects in Old Tafo
Construction of 3M X 1.5M Storm Drain 200M, 1.2M U-Drain (50M), 0.9M U-Drain (165M) And 0.6M U-Drain (50M) At Santan
Completed
Construction of Reinforced Concrete 1.5M X 1.5M Storm Drain At Tafo Abed In The Old Tafo Municipality (160m Long)
Completed
Construction Of Reinforced Concrete 2.5M X 2.0M Storm Drain At Tafo Mosque
Completed
Construction Of Reinforced Concrete 3.0M X 1.5M Storm Drain At Tafo Pankrono
Completed
Construction Of Reinforced Concrete Storm Drain At Tafo Ahenbrono
Completed
Constructoin Of Amangoase Road, Agric Ghana Road, Pankrono Road, Pankrono Roman Catholic Road, Adabraka Road And Osei Bonsu Road
Completed
View all sub-projects in Old Tafo
Sub-Project Details
Investment Type
Urban Road
Category
Works
Municipal Assembly
Old Tafo